## Task 4 - 040514

In Mücheln (Geisel Valley, District of Halle), the longest railway bridge in the GDR was completed. It consists of 7 identical bridge arches.

For one bridge arch, 147 m3147 \mathrm{~m}^{3} of concrete was used. 1 m31 \mathrm{~m}^{3} of concrete has a mass of 24dt24 \mathrm{dt}. How many tons of concrete were needed for the bridge construction? (Round to the nearest whole ton!)

A number or a short expression. Fractions can be typed as 3/2, and spacing doesn't matter.

Official solution

7 (arches) 147 m324dtm3=24696dt\cdot 147 \mathrm{~m}^{3} \cdot 24 \frac{\mathrm{dt}}{\mathrm{m}^{3}}=24696 \mathrm{dt}. In total, approximately 2470 tons of concrete are required.